Changing the revision number of an existing document

Under most circumstances, the revision number of an existing document will not need to be changed. That is, if the document is created new within the vault, Meridian Enterprise will assign the correct revision number. When the document is revised in a workflow, its revision number is updated accordingly. Even if existing documents are imported into the vault, as long as accurate metadata is imported or application link data exchange is configured, the revision numbers of documents should be correct. But occasionally there are circumstances when the revision number of a document must be changed manually.

Before you begin

You must be granted the Change Revision Number Manually privilege to perform this action.

To change the revision number of an existing document:

  1. Select the document that you want to change.
  2. Click the Document tab to display the Revision property.
  3. Click Edit. The Revision property becomes editable.
  4. Change the value of Revision and click OK.

Regardless of the current value of the Revision property, revisions of the document will display in chronological order in the Revisions dialog displayed by invoking the Show Revisions command.

Related tasks

Opening a document from within Meridian

Editing properties

Changing a document s type

Setting a property value

Issuing a new file name